Thursday, June 27, 2013

Patiently waiting................for handover

PCI done on 14th June. Today is Thursday 27th, almost 2 weeks and still no confirmation on handover. Little to no work has been done since.

Feeling well over numb and over being frustrated.


Wednesday, June 12, 2013

PCI Scheduled

Got a pleasant phone call from our SS this morning advising PCI and have scheduled a walkthrough on Friday morning.

Can't wait to see our house in detail and go over any issues if found and get them sorted.

Handover is expected one week from Friday which is the 21st June.

Fingers cross all goes to plan.

Oh, and our driveway is being cleaned and sealed today :)





Tuesday, June 11, 2013

Puzzle into Picture - Big month of June

We are heading down the finish line after many months of construction and delays.

The puzzle is soon becoming a picture......

Finally, our SS has advised that we are almost done, and a PCI (Practical Completion Inspection) will be booked shortly to run through the house in details. Also having an indepent inspector to go over the work in detail as well.

Early to mid May, had the interior painted a few coats as well as the stairs, followed by the tiles to ensuite, main bathroom and powder room which  is about 90% complete. Need the tiler to return to finish off niche tiles as they had to order extras. The tile work is quite good and happy with the majority but have questioned some issues and will have them brought up in the PCI.

End of May we finally got the fences removed and site cleaned up. Balcony has started with the Spotted Pine floating floor now visible. We are having the ceiling of the front entrance under the balcony finshed in spotted pine.

Bricks to side of house and exterior ender has been clean and painted. We are very happy on how the colours have turned out.

Early June, our lovely garage door has been installed in the timberlook coboa which has definately complimented to colours of the exterior. We are very stoked of the colours coming alive.

SS provided us the contact for the landscapers and got some additional work done on top of the driveway and porch. We wanted extra concrete the side to house as there isnt much sun there and is often damp after the wet weather. Waiting for the guys to return to do the sealing. We had paid to get some ag pipes done on the side so that water travels to the front garden. We also got some excavation work done in the rear to level the ground around our boundary.
We are certainly happy with the driveway, porch and side finish in the graphite grey colour.

We are really into the rustic, chic and retro look and focused around that type of styling.

As we are in "lock-up" and unable to access the house. We were fortunate to arrive onsite to see some tradies working and took advantage of taking some pictures.

Anyways, heres some updates in pictures, enjoy.

Ensuite:



Main Bathroom:



Main Bathroom shower and niche:



Powder room:



Exterior painted and garage installed:



Prep work for sideway and ag pipes for drainage:



And driveway:



Driveway and porch:









Thursday, April 4, 2013

It's been a while. But here's our update so far.

It's been a while since we had last posted. Had so many things happen in the past months. Getting married, honeymooning. Helping others..

We have come along way since our last 2012 update.

We will have the pictures tell the story. Bring on 2013

Enjoy.

Brickwork to the rear ground level alfresco


Brickwork to theatre


Brickwork complete, cladding to first level installed. Scaffold removed.


The inside, insulation installed as well as our beautiful cavity slide door separating the main entrance hallway to the kitchen/family room.


Insulation to the theatre wall to side of house


Insulation to our kitchen wall and window surround. 


Front study/lounge room window. We love it


We now have a front door


View from our front door hole


Hooray Gyprock completed

Kitchen/Family room



Kitchen fit out completed

Island without caesar stone 


Island with caesar stone


Kitchen...


Vanity for main bathroom


Vanity in ensuite


Our stairs


Balcony prepared using spotted gum wood.



How the house is to date.

There is a lot of dampness going through our front render due to the drainage pipes not connecting to the drain outlet. Therefore when wet, water running from the gutters are dropping onto the soil and condensation occurs into the render. Hope this get sorted out soon as its very ugly and may hinder the render and brick work for the future. RH said they will sort this out.













Friday, December 14, 2012

Colourbond roof + Render = Smiley Face

Spoke to our supervisor who advised that he will have one of the three colourbond roofs up before Xmas. Mate did he deliver. Main roof is up and the first level is now undercover from the xmas/boxing day weather approaching.

To our suprise, visited our site and booyah! Surfmist roof and rendered had started.









Rendered feature pillar:



Anticon roof insulation under the surfmist colourbond:



Stairway window now bricked.


Colourbond Surfmist Fascia:










Thats it for now folks.

More work to commence after the New Years break.